Announcement

Collapse
No announcement yet.

Estimating Construction Materials ... 1 sqm Wall of 4" CHB+Mortar (Cement + Sand) ...

Collapse
X
  • Filter
  • Time
  • Show
Clear All
new posts

  • Estimating Construction Materials ... 1 sqm Wall of 4" CHB+Mortar (Cement + Sand) ...


    i just found a bug in the mortar (cement and sand) computation of my estimate for a 1 sqm of wall using 4" CHB while i was reviewing the formula last night. the 0.0532 cubic meter of sand and 0.3133 bag of cement from my previous posting replies was WRONG. the 12.5 4" CHB for 1 sqm of wall is still CORRECT ...

    below is the correct computation for the estimate i did, after checking all my old notes from our house construction ... apologize for the wrong info before ...

    4" CHB dimension ... L=400mm x H=200mm x W=100mm (approx 16" x 8" x 4")

    dimension of 1 cavity in a 4" CHB ... 50mm x 90mm x 170mm

    i have remove the plastering and rebar (2 pcs of 1m lenght 9mm deformed rebar for 1 sqm of wall) in the estimation of a 1 sqm of wall as it makes more sense to compute the estimate of these items separately on a per wall basis based on the house/bldg plan.

    to get the amount of mortar required for a 1 sqm wall, first we need to estimate the area/volume in which the mortar will be put. these are:
    - a 4" CHB normally has 3 cavities each measuring an area of approx 90mm x 50mm x 170mm.
    - at the sides of a 4" CHB, you can also see a half-circle (or half-square) grove. if you set 2 CHB in a line with a 1/2" clearance between the 2 CHB, the area for the mortar can also be computed as approximately 1 cavity too. since each 1m (1000mm) length of wall will require about 2.5 CHB, this means another 3 cavities for the 2.5 CHBs in a row.
    - so total cavities (vertical area) per row will be 6 (for the 2 CHB) + 1.5 (for the 1/2 CHB) + 3 (for the 2.5 CHB per row) = 10.5 cavities.
    - the height of a CHB is approx 200mm, add the 1/2" (12mm) mortar height between rows, you have approx a 212mm height. in a 1m high wall, you will then need approx 5 rows (1000mm / 212mm = 4.72) of CHB.
    - the area for the mortar in between rows (horizontal area) of CHB will be about 1/2" (12mm) high with a lenght of 1000mm (1m) and a width of 100mm (4")

    using the same formula for computing concrete with a mix ratio of 1:6:0 (cement:sand:gravel) for mortar, you can then compute the total volume of concrete needed for the area of 1 sqm wall of 4" CHB ...
    - for each cavity (vertical area), the area/volume is ... {[(90*50*170) / 100000] / 10000} = 0.0008 cubic meter * 10.5 (number of cavities in a row) = 0.0080 cubic meter of concrete
    - for each row (horizontal area), the area/volume is ... {[(1000*100*12) / 100000] / 10000} = 0.0012 cubic meter * 5 (number of rows) = 0.0060 cubic meter of concrete
    - total volume = 0.0080 + 0.0060 = 0.0140 cubic meter of concrete for a 1 sqm wall

    having the concrete volume, we can then compute for the cement and sand using a mix ratio of 1:6:0 - gravel or aggregate is not needed for mortar ...

    so, to get the amount of cement needed for a 0.0140 cubic meters of concrete the formula is ... (volume * ratio of cement) / mixture total ratio ... (0.0140 * 1) / 7 = 0.0140/7 = 0.0020 cubic meter of cement ...

    so, to get the amount of sand needed for a 0.0140 cubic meters of concrete the formula is ... (volume * ratio of sand) / mixture total ratio ... (0.0140 * 6) / 7 = 0.084/7 = 0.012 cubic meter of sand ...

    in summary ... 0.0140 cubic meters of concrete with a ratio of 1:6:0 will require ...
    0.0020 of cement
    0.0120 of sand
    --------
    0.0140 cubic meters of concrete (total) ...

    to convert the amount of cement into bags of cement ... just multiply the cement in cubic meters by 35.31 ... 0.0020 * 35.31 = 0.0708 bags of cement ...

    cheers ...

    Boo!


  • #2
    hi boo-semi-retired!

    thanks for this post and it really helps a lot.
    i want to make a calculation on my own since i felt i was being ripped off by our foreman with the materials before since i was not on the site most of the time.So on our next project i want to be there.lesson learned.

    So based on the formula you provide i came up with this and correct me if i'm wrong pls.

    1 cu. mtr of sand could be divided into 8 parts based on 0.0120 sand per sq mtr of wall.

    0.0708 bag of cement multiply by 8 is 5.6 bag of cement or round it to 6 bags.

    with a ratio of 1:6:0 for mortar
    1 cubic mtr of sand + 6 bags of cement can fill 8 sq. mtrs of CHB wall.

    is my computation right?and please bear with me on this.

    thanks in advance

    Comment


    • Boo-Semi-Retired
      Boo-Semi-Retired commented
      Editing a comment
      yes, your computation is right if you want to get an estimate base on a cubic meter of sand. don't forget to allocate some percentage for wastage and other factors. in my case, in our house construction, i use a 10% variance for wastage ... cheers

      Boo!

  • #3
    thank you so much.i'm working on my calculation bit by bit.i also used your formula for plastering.
    at least in 2 mnths time i could gather all the info needed and my foreman would be surprised that a woman like me knows a little bit of this and that and i won't be ripped off again!

    Comment

    Related Articles

    Collapse

    Collapse
    • Filter
    • Time
    • Show
    • New Topics
    Clear All
    new posts
    No content found
    Show More
    • Filter
    • Time
    • Show
    • New Topics
    Clear All
    new posts
    Please log in to your account to view your subscribed posts.

    Related Articles

    Collapse

    Working...
    X